Well house is up and level. Lots of cracks in the walls. The house moved away from the garage section by 2" so we now have a gap between the two sections that will need to be repaired. Pouring the footing monday and the new stem walls by wednesday. None of the doors will open, only the large garage door since it is not expected by the lifting of the house.